Consulting Civil and Environmental Engineers Since 1972

Bridges | Municipal Engineering | Roads | Site Planning | Wastewater | Water Supply | Land Survey
     Projects     

Portland / MDC Interconnection
Portland, Connecticut

THE CHALLENGE: After years of struggling for a solution to their water supply source treatment requirements, the Portland Connecticut Water Division achieved a solution through an interconnection with the Metropolitan District Commission (MDC).

THE SOLUTION: The initial process of the interconnection was to determine the physical and financial feasibility. The Portland water system was modeled to determine what system improvements would be required to connect to the Metropolitan District. Water mains of each Authority were in economical proximity to one another, but system improvements were required to convey the 2-mgd flow required for Portland's current and future needs. The modeling study identified size and location of new transmission mains and storage tanks as well as required hydraulic grade lines for a booster pumping station in the Metropolitan District system. With the required improvements considered, project costs were estimated and an economic analysis made for the project..

With a firm understanding of the costs and benefits, the Town of Portland negotiated a long-term contract with the MDC and proceeded with co-applicant MDC in the pursuit of a Diversion permit from the Connecticut Department of Environmental Protection. Obtaining this permit was a most critical element to this project's success. Nathan L. Jacobson & Associates, Inc. provided technical support to the Portland Water Division through this lengthy process and negotiations with stakeholders. Once the permit was issued, the preparation of the construction contract documents was begun.

Contract 1 was a construction contract for approximately 1-1/2 miles of 16-inch diameter water transmission main in two different Portland locations. Nathan L. Jacobson & Associates, Inc. prepared the contract documents and provided construction inspection and administration services.

 

Contract 2 was a construction contract for approximately 1-mile of 16-inch diameter water transmission main in Glastonbury with a meter and valve chamber constructed on the Portland / Glastonbury Town line. The MDC provided administration of this contract.

Contract 3 was issued for the construction of two 0.5 million gallon water storage tanks. Steel tanks with a three-coat interior epoxy paint finish and a cathodic protection system were chosen for the application. The access drive to the tank site required construction of a timber bridge with 25 foot clear span over Reservoir Brook. To preserve distribution system water quality, recirculation pumps were provided to promote turnover of the tanks and chlorination facilities were provided on the site. The contract included a control system for tank level monitoring and control of a well pump and an electric butterfly valve at the connection to the MDC. The system provides for remote monitoring of flow obtained from the MDC, tank level, and chlorine residual at the tank. Nathan L. Jacobson & Associates, Inc. prepared the contract documents and provided construction inspection and administration services as well as start-up services.

After 16 months of construction, the project was completed in 2000 at a cost of approximately $3.0 million.



86 Main Street
P.O. Box 337
Chester, Connecticut  06412-0337
860-526-9591 (phone)
860-526-5416 (fax)
E-mail


Project Index | Top | Next Project